ABR-1000 Variables

ABR-1000 Variables

Index

Name

Description

Unit

1

c_213_fac

Turbine building structure factory cost

million

2

c_213_lab

Turbine building structure labor cost

million

3

c_213_mat

Turbine building structure material cost

million

4

c_220A.2121_ss_weight

weight of the stainless steel lower internals

ton

5

c_220A.2122_ss_weight

weight of the stainless steel upper internals

ton

6

c_220A.222_ss_weight

weight of the stainless steel reactor coolant piping

ton

7

c_222_fac

Main heat transfer transport system factory cost

million

8

c_222_lab

Main heat transfer transport system labor cost

million

9

c_222_mat

Main heat transfer transport system material cost

million

10

c_222.11_fac

Fluid Circulation Drive System (Field Cost 222) factory cost

million

11

c_222.11_lab

Fluid Circulation Drive System (Field Cost 222) labor cost

million

12

c_222.11_mat

Fluid Circulation Drive System (Field Cost 222) material cost

million

13

c_222.12_fac

Reactor Coolant Piping System (Field Cost 222) factory cost

million

14

c_222.12_lab

Reactor Coolant Piping System (Field Cost 222) labor cost

million

15

c_222.12_mat

Reactor Coolant Piping System (Field Cost 222) material cost

million

16

c_222.13_fac

Steam Generator Equipment (Field Cost 222) factory cost

million

17

c_222.14_fac

Pressurizing System (Field Cost 222) factory cost

million

18

c_222.14_lab

Pressurizing System (Field Cost 222) labor cost

million

19

c_222.14_mat

Pressurizing System (Field Cost 222) material cost

million

20

c_231_fac

Turbine factory cost

million

21

c_231_lab

Turbine labor cost

million

22

c_231_mat

Turbine material cost

million

23

c_233_fac

Condensing Systems factory cost

million

24

c_233_lab

Condensing Systems labor cost

million

25

c_233_mat

Condensing Systems material cost

million

26

c_241_fac

Switchgear factory cost

million

27

c_241_lab

Switchgear labor cost

million

28

c_241_mat

Switchgear material cost

million

29

c_242_fac

Station service equipment factory cost

million

30

c_242_lab

Station service equipment labor cost

million

31

c_242_mat

Station service equipment material cost

million

32

c_245_fac

Electric structure and wiring contnr. factory cost

million

33

c_245_lab

Electric structure and wiring contnr. labor cost

million

34

c_245_mat

Electric structure and wiring contnr. material cost

million

35

c_246_fac

Power and control wiring factory cost

million

36

c_246_lab

Power and control wiring labor cost

million

37

c_246_mat

Power and control wiring material cost

million

38

c_262_fac

Heat Rejection System factory cost

million

39

c_262_lab

Heat Rejection System labor cost

million

40

c_262_mat

Heat Rejection System material cost

million

41

c_cr_per_unit_fac

unit cost of rod

million

42

c_crd_per_unit_fac

unit cost of rod drive

million

43

c_pump_ap1000

AP1000 factory cost of main coolant pumps

million

44

c_pump_per_unit_fac

Reactor coolant pumps Factory Equipment Cost

million

45

c_turbine

Turbine equipment cost

million

46

c_zero

place holder for weight

ton

47

CH_abr1000

CH factor of PWR-12 BE

gpm*feet

48

CH_AP1000

CH factor of AP1000

gpm*feet

49

escalate_1987

escalator 1987 to 2017

1

50

mwe

user_input MWE

MW

51

mwreth

rejected thermal power

MW

52

mwth

user_input mwth

MW

53

no_of_cr

Total control rods

1

54

no_of_crd

Total control rod drives

1

55

no_of_rcpump

total number of reactor coolant pumps

1

56

prn_235_of_231_fac

factory portion of cost from factory of 231

1

57

prn_235_of_231_lab

labor portion of cost from labor of 231

1

58

prn_235_of_231_mat

material portion of cost from labor of 231

1

59

prn_fac_231_lab

labor portion of cost from factory of 231

1

60

prn_fac_231_mat

material portion of cost from factory of 231

1

61

r_222.13_lab

labor cost of Steam Generator Equipment (Field Cost 222)

million

62

r_222.13_mat

material cost of Steam Generator Equipment (Field Cost 222)

million

63

r_78_220A224_fac

factory cost of pressurizer in ref

million

64

r_78_226.4_fac

Coolant Treatment & Recycle factory cost

million

65

ref_211_fac

yardwork factory cost

million

66

ref_211_lab

yardwork labor cost

million

67

ref_211_mat

yardwork material cost

million

68

ref_224_fac

Radwaste processing factory cost

million

69

ref_224_lab

Radwaste processing labor cost

million

70

ref_224_mat

Radwaste processing material cost

million

71

ref_227_fac

Reactor instrumentation and control factory cost

million

72

ref_227_lab

Reactor instrumentation and control labor cost

million

73

ref_227_mat

Reactor instrumentation and control material cost

million

74

ref_252_fac

Air, water and steam service systems factory cost

million

75

ref_252_lab

Air, water and steam service systems labor cost

million

76

ref_252_mat

Air, water and steam service systems material cost

million

77

scale_0.4

electric scale 0.4

1

78

scale_0.52

SH scale 1.0

1

79

scale_0.8

thermal scale 0.8

1

80

scale_1.0

thermal scale 1.0

1

81

scale_tur_231_fac

factory scale of cost from turbine

1

82

CPI

The Consumer Price Index

1

83

Void_fraction

Void fraction of the inside of the containment

1

84

liner_fraction

liner fraction of containment

1

85

Cont_H_tot_m

Containment total height

m

86

Cont_rad_out_m

Containment outside radius

m

87

Cont_shell_t_m

Shell wall thickness

m

88

Cont_H_wall_m

Containment wall height

m

89

Basemat_t_m

Basemat thickness

m

90

Dome_t_m

Dome thickness

m

91

Intern_wall_t

Internal wall average thickness

m

92

React_cav_A_m2

Reactor cavity area

m^2

93

Cont_rad_in_m

Containment inside radius

m

94

Basemat_s_m2

Basemat surface

m^2

95

Basemat_v_m3

Basemat volume

m^3

96

Walls_s_m2

Walls surface

m^2

97

Walls_v_m3

Walls volume

m^3

98

Dome_rad_in_m

Dome inside radius

m

99

Dome_s_m2

Roof surface

m^2

100

Dome_v_m3

Roof volume

m^3

101

Intern_tot_v_m3

Tot intenal Volume

m^3

102

Internal_v_m3

Building internal volume

m^3

103

Internal_s_m2

Building internal surface

m^2

104

Struct_v_m3

volume of the structures

m^3

105

Inside_liner_s

Inside liner surface

m^2

106

Liner_s_m2

Liner Surface

m^2

107

Surf_paint_m2

painted surface

m^2

108

infl

Inflation rate

1

109

Unit_EEDB_Labor_Cadweld_Substr

Unit cost of Labor Cadweld Substructure (base mat) in EEDB

dollar/m^3

110

Unit_EEDB_Labor_Cadweld_Superstr

Unit cost of Labor Cadweld Superstructure (shell) in EEDB

dollar/m^3

111

Unit_EEDB_Labor_Cadweld_Dome

Unit cost of Labor Cadweld Superstructure (dome) in EEDB

dollar/m^3

112

Unit_EEDB_Labor_Cadweld_Interior

Unit cost of Labor Cadweld Interior structure in EEDB

dollar/m^3

113

Unit_EEDB_Labor_Concrete_Substr

Unit cost of Labor Concrete Substructure (base mat) in EEDB

dollar/m^3

114

Unit_EEDB_Labor_Concrete_Superstr

Unit cost of Labor Concrete Superstructure (shell) in EEDB

dollar/m^3

115

Unit_EEDB_Labor_Concrete_Dome

Unit cost of Labor Concrete Superstructure (dome) in EEDB

dollar/m^3

116

Unit_EEDB_Labor_Concrete_Interior

Unit cost of Labor Concrete Interior structure in EEDB

dollar/m^3

117

Unit_EEDB_Labor_Constr_joints_Substr

Unit cost of Labor Construction joints Substructure (base mat) in EEDB

dollar/m^2

118

Unit_EEDB_Labor_Constr_joints_Superstr

Unit cost of Labor Construction joints Superstructure (shell) in EEDB

dollar/m^2

119

Unit_EEDB_Labor_Constr_joints_Dome

Unit cost of Labor Construction joints Superstructure (dome) in EEDB

dollar/m^2

120

Unit_EEDB_Labor_Constr_joints_Interior

Unit cost of Labor Construction joints Interior structure in EEDB

dollar/m^2

121

Unit_EEDB_Labor_Embedded_steel_Substr

Unit cost of Labor Embedded steel Substructure (base mat) in EEDB

dollar/m^3

122

Unit_EEDB_Labor_Embedded_steel_Superstr

Unit cost of Labor Embedded steel Superstructure (shell) in EEDB

dollar/m^3

123

Unit_EEDB_Labor_Embedded_steel_Dome

Unit cost of Labor Embedded steel Superstructure (dome) in EEDB

dollar/m^3

124

Unit_EEDB_Labor_Embedded_steel_Interior

Unit cost of Labor Embedded steel Interior structure in EEDB

dollar/m^3

125

Unit_EEDB_Labor_Formwork_Substr

Unit cost of Labor Formwork Substructure (base mat) in EEDB

dollar/m^2

126

Unit_EEDB_Labor_Formwork_Superstr

Unit cost of Labor Formwork Superstructure (shell) in EEDB

dollar/m^2

127

Unit_EEDB_Labor_Formwork_Dome

Unit cost of Labor Formwork Superstructure (dome) in EEDB

dollar/m^2

128

Unit_EEDB_Labor_Formwork_Interior

Unit cost of Labor Formwork Interior structure in EEDB

dollar/m^2

129

Unit_EEDB_Labor_Maj_supp_embedments_Interior

Unit cost of Labor Major Support Embedments Interior structure in EEDB

dollar/m^3

130

Unit_EEDB_Labor_Reinforc_steel_Substr

Unit cost of Labor Reinforc steel Substructure (base mat) in EEDB

dollar/m^3

131

Unit_EEDB_Labor_Reinforc_steel_Superstr

Unit cost of Labor Reinforc steel Superstructure (shell) in EEDB

dollar/m^3

132

Unit_EEDB_Labor_Reinforc_steel_Dome

Unit cost of Labor Reinforc steel Superstructure (dome) in EEDB

dollar/m^3

133

Unit_EEDB_Labor_Reinforc_steel_Interior

Unit cost of Labor Reinforc steel Interior structure in EEDB

dollar/m^3

134

Unit_EEDB_Labor_Rubbing_surfaces_Superstr

Unit cost of Labor Rubbing surfaces Superstructure (shell) in EEDB

dollar/m^2

135

Unit_EEDB_Labor_Rubbing_surfaces_Dome

Unit cost of Labor Rubbing surfaces Superstructure (dome) in EEDB

dollar/m^2

136

Unit_EEDB_Labor_Rubbing_surfaces_Interior

Unit cost of Labor Rubbing surfaces Interior structure in EEDB

dollar/m^2

137

Unit_EEDB_Labor_Waterproofing_Substr

Unit cost of Labor Waterproofing Substructure (base mat) in EEDB

dollar/m^2

138

Unit_EEDB_Labor_Waterproofing_Superstr

Unit cost of Labor Waterproofing Superstructure (shell) in EEDB

dollar/m^2

139

Unit_EEDB_Labor_Waterproofing_Dome

Unit cost of Labor Waterproofing Superstructure (dome) in EEDB

dollar/m^2

140

Unit_EEDB_Labor_Welded_wire_fabric_Substr

Unit cost of Labor Welded wire fabric Substructure (base mat) in EEDB

dollar/m^2

141

Unit_EEDB_Labor_Lighting_Power

Unit cost of Labor Lighting Power in EEDB

dollar/m^3

142

Unit_EEDB_Labor_Plumb_drains

Unit cost of Labor Plumb drains in EEDB

dollar/m^3

143

Unit_EEDB_Labor_Special_HVAC

Unit cost of Labor Special HVAC in EEDB

dollar/m^3

144

Unit_EEDB_Labor_other

Unit cost of Labor other in EEDB

dollar/m^3

145

Unit_EEDB_Labor_Misc_steel_frames

Unit cost of Labor miscellaneous steel frames in EEDB

dollar/m^3

146

Unit_EEDB_Labor_React_cav_liner

Unit cost of Labor Reactor cavity liner plate in EEDB

dollar/m^2

147

Unit_EEDB_Labor_Struct_steel

Unit cost of Labor Struct steel in EEDB

dollar/m^3

148

Unit_EEDB_Labor_cont_liner

Unit cost of Labor Containment liner in EEDB

dollar/m^2

149

Unit_EEDB_Labor_fl_grate_handrail_stairs

Unit cost of Labor Floor grating (galvanized), Handrail, Stair treads in EEDB

dollar/m^3

150

Unit_EEDB_Labor_painting

Unit cost of Labor painting in EEDB

dollar/m^2

151

Unit_EEDB_Mat_Cadweld_Substr

Unit cost of Material Cadweld Substructure (base mat) in EEDB

dollar/m^3

152

Unit_EEDB_Mat_Cadweld_Superstr

Unit cost of Material Cadweld Superstructure (shell) in EEDB

dollar/m^3

153

Unit_EEDB_Mat_Cadweld_Dome

Unit cost of Material Cadweld Superstructure (dome) in EEDB

dollar/m^3

154

Unit_EEDB_Mat_Cadweld_Interior

Unit cost of Material Cadweld Interior structure in EEDB

dollar/m^3

155

Unit_EEDB_Mat_Concrete_Substr

Unit cost of Material Concrete Substructure (base mat) in EEDB

dollar/m^3

156

Unit_EEDB_Mat_Concrete_Superstr

Unit cost of Material Concrete Superstructure (shell) in EEDB

dollar/m^3

157

Unit_EEDB_Mat_Concrete_Dome

Unit cost of Material Concrete Superstructure (dome) in EEDB

dollar/m^3

158

Unit_EEDB_Mat_Concrete_Interior

Unit cost of Material Concrete Interior structure in EEDB

dollar/m^3

159

Unit_EEDB_Mat_Constr_joints_Substr

Unit cost of Material Construction joints Substructure (base mat) in EEDB

dollar/m^2

160

Unit_EEDB_Mat_Constr_joints_Superstr

Unit cost of Material Construction joints Superstructure (shell) in EEDB

dollar/m^2

161

Unit_EEDB_Mat_Constr_joints_Dome

Unit cost of Material Construction joints Superstructure (dome) in EEDB

dollar/m^2

162

Unit_EEDB_Mat_Constr_joints_Interior

Unit cost of Material Construction joints Interior structure in EEDB

dollar/m^2

163

Unit_EEDB_Mat_Embedded_steel_Substr

Unit cost of Material Embedded steel Substructure (base mat) in EEDB

dollar/m^3

164

Unit_EEDB_Mat_Embedded_steel_Superstr

Unit cost of Material Embedded steel Superstructure (shell) in EEDB

dollar/m^3

165

Unit_EEDB_Mat_Embedded_steel_Dome

Unit cost of Material Embedded steel Superstructure (dome) in EEDB

dollar/m^3

166

Unit_EEDB_Mat_Embedded_steel_Interior

Unit cost of Material Embedded steel Interior structure in EEDB

dollar/m^3

167

Unit_EEDB_Mat_Formwork_Substr

Unit cost of Material Formwork Substructure (base mat) in EEDB

dollar/m^2

168

Unit_EEDB_Mat_Formwork_Superstr

Unit cost of Material Formwork Superstructure (shell) in EEDB

dollar/m^2

169

Unit_EEDB_Mat_Formwork_Dome

Unit cost of Material Formwork Superstructure (dome) in EEDB

dollar/m^2

170

Unit_EEDB_Mat_Formwork_Interior

Unit cost of Material Formwork Interior structure in EEDB

dollar/m^2

171

Unit_EEDB_Mat_Maj_supp_embedments_Interior

Unit cost of Material Major Support Embedments Interior structure in EEDB

dollar/m^3

172

Unit_EEDB_Mat_Reinforc_steel_Substr

Unit cost of Material Reinforc steel Substructure (base mat) in EEDB

dollar/m^3

173

Unit_EEDB_Mat_Reinforc_steel_Superstr

Unit cost of Material Reinforc steel Superstructure (shell) in EEDB

dollar/m^3

174

Unit_EEDB_Mat_Reinforc_steel_Dome

Unit cost of Material Reinforc steel Superstructure (dome) in EEDB

dollar/m^3

175

Unit_EEDB_Mat_Reinforc_steel_Interior

Unit cost of Material Reinforc steel Interior structure in EEDB

dollar/m^3

176

Unit_EEDB_Mat_Rubbing_surfaces_Superstr

Unit cost of Material Rubbing surfaces Superstructure (shell) in EEDB

dollar/m^2

177

Unit_EEDB_Mat_Rubbing_surfaces_Dome

Unit cost of Material Rubbing surfaces Superstructure (dome) in EEDB

dollar/m^2

178

Unit_EEDB_Mat_Rubbing_surfaces_Interior

Unit cost of Material Rubbing surfaces Interior structure in EEDB

dollar/m^2

179

Unit_EEDB_Mat_Waterproofing_Substr

Unit cost of Material Waterproofing Substructure (base mat) in EEDB

dollar/m^2

180

Unit_EEDB_Mat_Waterproofing_Superstr

Unit cost of Material Waterproofing Superstructure (shell) in EEDB

dollar/m^2

181

Unit_EEDB_Mat_Waterproofing_Dome

Unit cost of Material Waterproofing Superstructure (dome) in EEDB

dollar/m^2

182

Unit_EEDB_Mat_Welded_wire_fabric_Substr

Unit cost of Material Welded wire fabric Substructure (base mat) in EEDB

dollar/m^2

183

Unit_EEDB_Mat_Lighting_Power

Unit cost of Material Lighting Power in EEDB

dollar/m^3

184

Unit_EEDB_Mat_Plumb_drains

Unit cost of Material Plumb drains in EEDB

dollar/m^3

185

Unit_EEDB_Mat_Special_HVAC

Unit cost of Material Special HVAC in EEDB

dollar/m^3

186

Unit_EEDB_Mat_other

Unit cost of Material other in EEDB

dollar/m^3

187

Unit_EEDB_Mat_Misc_steel_frames

Unit cost of Material miscellaneous steel frames in EEDB

dollar/m^3

188

Unit_EEDB_Mat_React_cav_liner

Unit cost of Material Reactor cavity liner plate in EEDB

dollar/m^2

189

Unit_EEDB_Mat_Struct_steel

Unit cost of Material Struct steel in EEDB

dollar/m^3

190

Unit_EEDB_Mat_cont_liner

Unit cost of Material Containment liner in EEDB

dollar/m^2

191

Unit_EEDB_Mat_fl_grate_handrail_stairs

Unit cost of Material Floor grating (galvanized), Handrail, Stair treads in EEDB

dollar/m^3

192

Unit_EEDB_Mat_painting

Unit cost of Material painting in EEDB

dollar/m^2

193

Unit_Labor_Cadweld_Substr

Unit cost of Labor Cadweld Substructure (base mat) in 2017

dollar/m^3

194

Unit_Labor_Cadweld_Superstr

Unit cost of Labor Cadweld Superstructure (shell) in 2017

dollar/m^3

195

Unit_Labor_Cadweld_Dome

Unit cost of Labor Cadweld Superstructure (dome) in 2017

dollar/m^3

196

Unit_Labor_Cadweld_Interior

Unit cost of Labor Cadweld Interior structure in 2017

dollar/m^3

197

Unit_Labor_Concrete_Substr

Unit cost of Labor Concrete Substructure (base mat) in 2017

dollar/m^3

198

Unit_Labor_Concrete_Superstr

Unit cost of Labor Concrete Superstructure (shell) in 2017

dollar/m^3

199

Unit_Labor_Concrete_Dome

Unit cost of Labor Concrete Superstructure (dome) in 2017

dollar/m^3

200

Unit_Labor_Concrete_Interior

Unit cost of Labor Concrete Interior structure in 2017

dollar/m^3

201

Unit_Labor_Constr_joints_Substr

Unit cost of Labor Construction joints Substructure (base mat) in 2017

dollar/m^2

202

Unit_Labor_Constr_joints_Superstr

Unit cost of Labor Construction joints Superstructure (shell) in 2017

dollar/m^2

203

Unit_Labor_Constr_joints_Dome

Unit cost of Labor Construction joints Superstructure (dome) in 2017

dollar/m^2

204

Unit_Labor_Constr_joints_Interior

Unit cost of Labor Construction joints Interior structure in 2017

dollar/m^2

205

Unit_Labor_Embedded_steel_Substr

Unit cost of Labor Embedded steel Substructure (base mat) in 2017

dollar/m^3

206

Unit_Labor_Embedded_steel_Superstr

Unit cost of Labor Embedded steel Superstructure (shell) in 2017

dollar/m^3

207

Unit_Labor_Embedded_steel_Dome

Unit cost of Labor Embedded steel Superstructure (dome) in 2017

dollar/m^3

208

Unit_Labor_Embedded_steel_Interior

Unit cost of Labor Embedded steel Interior structure in 2017

dollar/m^3

209

Unit_Labor_Formwork_Substr

Unit cost of Labor Formwork Substructure (base mat) in 2017

dollar/m^2

210

Unit_Labor_Formwork_Superstr

Unit cost of Labor Formwork Superstructure (shell) in 2017

dollar/m^2

211

Unit_Labor_Formwork_Dome

Unit cost of Labor Formwork Superstructure (dome) in 2017

dollar/m^2

212

Unit_Labor_Formwork_Interior

Unit cost of Labor Formwork Interior structure in 2017

dollar/m^2

213

Unit_Labor_Maj_supp_embedments_Interior

Unit cost of Labor Major Support Embedments Interior structure in 2017

dollar/m^3

214

Unit_Labor_Reinforc_steel_Substr

Unit cost of Labor Reinforc steel Substructure (base mat) in 2017

dollar/m^3

215

Unit_Labor_Reinforc_steel_Superstr

Unit cost of Labor Reinforc steel Superstructure (shell) in 2017

dollar/m^3

216

Unit_Labor_Reinforc_steel_Dome

Unit cost of Labor Reinforc steel Superstructure (dome) in 2017

dollar/m^3

217

Unit_Labor_Reinforc_steel_Interior

Unit cost of Labor Reinforc steel Interior structure in 2017

dollar/m^3

218

Unit_Labor_Rubbing_surfaces_Superstr

Unit cost of Labor Rubbing surfaces Superstructure (shell) in 2017

dollar/m^2

219

Unit_Labor_Rubbing_surfaces_Dome

Unit cost of Labor Rubbing surfaces Superstructure (dome) in 2017

dollar/m^2

220

Unit_Labor_Rubbing_surfaces_Interior

Unit cost of Labor Rubbing surfaces Interior structure in 2017

dollar/m^2

221

Unit_Labor_Waterproofing_Substr

Unit cost of Labor Waterproofing Substructure (base mat) in 2017

dollar/m^2

222

Unit_Labor_Waterproofing_Superstr

Unit cost of Labor Waterproofing Superstructure (shell) in 2017

dollar/m^2

223

Unit_Labor_Waterproofing_Dome

Unit cost of Labor Waterproofing Superstructure (dome) in 2017

dollar/m^2

224

Unit_Labor_Welded_wire_fabric_Substr

Unit cost of Labor Welded wire fabric Substructure (base mat) in 2017

dollar/m^2

225

Unit_Labor_Lighting_Power

Unit cost of Labor Lighting Power in 2017

dollar/m^3

226

Unit_Labor_Plumb_drains

Unit cost of Labor Plumb drains in 2017

dollar/m^3

227

Unit_Labor_Special_HVAC

Unit cost of Labor Special HVAC in 2017

dollar/m^3

228

Unit_Labor_other

Unit cost of Labor other in 2017

dollar/m^3

229

Unit_Labor_Misc_steel_frames

Unit cost of Labor miscellaneous steel frames in 2017

dollar/m^3

230

Unit_Labor_React_cav_liner

Unit cost of Labor Reactor cavity liner plate in 2017

dollar/m^2

231

Unit_Labor_Struct_steel

Unit cost of Labor Struct steel in 2017

dollar/m^3

232

Unit_Labor_cont_liner

Unit cost of Labor Containment liner in 2017

dollar/m^2

233

Unit_Labor_fl_grate_handrail_stairs

Unit cost of Labor Floor grating (galvanized), Handrail, Stair treads in 2017

dollar/m^3

234

Unit_Labor_painting

Unit cost of Labor painting in 2017

dollar/m^2

235

Unit_Mat_Cadweld_Substr

Unit cost of Material Cadweld Substructure (base mat) in 2017

dollar/m^3

236

Unit_Mat_Cadweld_Superstr

Unit cost of Material Cadweld Superstructure (shell) in 2017

dollar/m^3

237

Unit_Mat_Cadweld_Dome

Unit cost of Material Cadweld Superstructure (dome) in 2017

dollar/m^3

238

Unit_Mat_Cadweld_Interior

Unit cost of Material Cadweld Interior structure in 2017

dollar/m^3

239

Unit_Mat_Concrete_Substr

Unit cost of Material Concrete Substructure (base mat) in 2017

dollar/m^3

240

Unit_Mat_Concrete_Superstr

Unit cost of Material Concrete Superstructure (shell) in 2017

dollar/m^3

241

Unit_Mat_Concrete_Dome

Unit cost of Material Concrete Superstructure (dome) in 2017

dollar/m^3

242

Unit_Mat_Concrete_Interior

Unit cost of Material Concrete Interior structure in 2017

dollar/m^3

243

Unit_Mat_Constr_joints_Substr

Unit cost of Material Construction joints Substructure (base mat) in 2017

dollar/m^2

244

Unit_Mat_Constr_joints_Superstr

Unit cost of Material Construction joints Superstructure (shell) in 2017

dollar/m^2

245

Unit_Mat_Constr_joints_Dome

Unit cost of Material Construction joints Superstructure (dome) in 2017

dollar/m^2

246

Unit_Mat_Constr_joints_Interior

Unit cost of Material Construction joints Interior structure in 2017

dollar/m^2

247

Unit_Mat_Embedded_steel_Substr

Unit cost of Material Embedded steel Substructure (base mat) in 2017

dollar/m^3

248

Unit_Mat_Embedded_steel_Superstr

Unit cost of Material Embedded steel Superstructure (shell) in 2017

dollar/m^3

249

Unit_Mat_Embedded_steel_Dome

Unit cost of Material Embedded steel Superstructure (dome) in 2017

dollar/m^3

250

Unit_Mat_Embedded_steel_Interior

Unit cost of Material Embedded steel Interior structure in 2017

dollar/m^3

251

Unit_Mat_Formwork_Substr

Unit cost of Material Formwork Substructure (base mat) in 2017

dollar/m^2

252

Unit_Mat_Formwork_Superstr

Unit cost of Material Formwork Superstructure (shell) in 2017

dollar/m^2

253

Unit_Mat_Formwork_Dome

Unit cost of Material Formwork Superstructure (dome) in 2017

dollar/m^2

254

Unit_Mat_Formwork_Interior

Unit cost of Material Formwork Interior structure in 2017

dollar/m^2

255

Unit_Mat_Maj_supp_embedments_Interior

Unit cost of Material Major Support Embedments Interior structure in 2017

dollar/m^3

256

Unit_Mat_Reinforc_steel_Substr

Unit cost of Material Reinforc steel Substructure (base mat) in 2017

dollar/m^3

257

Unit_Mat_Reinforc_steel_Superstr

Unit cost of Material Reinforc steel Superstructure (shell) in 2017

dollar/m^3

258

Unit_Mat_Reinforc_steel_Dome

Unit cost of Material Reinforc steel Superstructure (dome) in 2017

dollar/m^3

259

Unit_Mat_Reinforc_steel_Interior

Unit cost of Material Reinforc steel Interior structure in 2017

dollar/m^3

260

Unit_Mat_Rubbing_surfaces_Superstr

Unit cost of Material Rubbing surfaces Superstructure (shell) in 2017

dollar/m^2

261

Unit_Mat_Rubbing_surfaces_Dome

Unit cost of Material Rubbing surfaces Superstructure (dome) in 2017

dollar/m^2

262

Unit_Mat_Rubbing_surfaces_Interior

Unit cost of Material Rubbing surfaces Interior structure in 2017

dollar/m^2

263

Unit_Mat_Waterproofing_Substr

Unit cost of Material Waterproofing Substructure (base mat) in 2017

dollar/m^2

264

Unit_Mat_Waterproofing_Superstr

Unit cost of Material Waterproofing Superstructure (shell) in 2017

dollar/m^2

265

Unit_Mat_Waterproofing_Dome

Unit cost of Material Waterproofing Superstructure (dome) in 2017

dollar/m^2

266

Unit_Mat_Welded_wire_fabric_Substr

Unit cost of Material Welded wire fabric Substructure (base mat) in 2017

dollar/m^2

267

Unit_Mat_Lighting_Power

Unit cost of Material Lighting Power in 2017

dollar/m^3

268

Unit_Mat_Plumb_drains

Unit cost of Material Plumb drains in 2017

dollar/m^3

269

Unit_Mat_Special_HVAC

Unit cost of Material Special HVAC in 2017

dollar/m^3

270

Unit_Mat_other

Unit cost of Material other in 2017

dollar/m^3

271

Unit_Mat_Misc_steel_frames

Unit cost of Material miscellaneous steel frames in 2017

dollar/m^3

272

Unit_Mat_React_cav_liner

Unit cost of Material Reactor cavity liner plate in 2017

dollar/m^2

273

Unit_Mat_Struct_steel

Unit cost of Material Struct steel in 2017

dollar/m^3

274

Unit_Mat_cont_liner

Unit cost of Material Containment liner in 2017

dollar/m^2

275

Unit_Mat_fl_grate_handrail_stairs

Unit cost of Material Floor grating (galvanized), Handrail, Stair treads in 2017

dollar/m^3

276

Unit_Mat_painting

Unit cost of Material painting in 2017

dollar/m^2

277

Total_Labor_Cadweld_Substr

Total cost of Labor Cadweld Substructure (base mat) in 2017

dollar

278

Total_Labor_Cadweld_Superstr

Total cost of Labor Cadweld Superstructure (shell) in 2017

dollar

279

Total_Labor_Cadweld_Dome

Total cost of Labor Cadweld Superstructure (dome) in 2017

dollar

280

Total_Labor_Cadweld_Interior

Total cost of Labor Cadweld Interior structure in 2017

dollar

281

Total_Labor_Concrete_Substr

Total cost of Labor Concrete Substructure (base mat) in 2017

dollar

282

Total_Labor_Concrete_Superstr

Total cost of Labor Concrete Superstructure (shell) in 2017

dollar

283

Total_Labor_Concrete_Dome

Total cost of Labor Concrete Superstructure (dome) in 2017

dollar

284

Total_Labor_Concrete_Interior

Total cost of Labor Concrete Interior structure in 2017

dollar

285

Total_Labor_Constr_joints_Substr

Total cost of Labor Construction joints Substructure (base mat) in 2017

dollar

286

Total_Labor_Constr_joints_Superstr

Total cost of Labor Construction joints Superstructure (shell) in 2017

dollar

287

Total_Labor_Constr_joints_Dome

Total cost of Labor Construction joints Superstructure (dome) in 2017

dollar

288

Total_Labor_Constr_joints_Interior

Total cost of Labor Construction joints Interior structure in 2017

dollar

289

Total_Labor_Embedded_steel_Substr

Total cost of Labor Embedded steel Substructure (base mat) in 2017

dollar

290

Total_Labor_Embedded_steel_Superstr

Total cost of Labor Embedded steel Superstructure (shell) in 2017

dollar

291

Total_Labor_Embedded_steel_Dome

Total cost of Labor Embedded steel Superstructure (dome) in 2017

dollar

292

Total_Labor_Embedded_steel_Interior

Total cost of Labor Embedded steel Interior structure in 2017

dollar

293

Total_Labor_Formwork_Substr

Total cost of Labor Formwork Substructure (base mat) in 2017

dollar

294

Total_Labor_Formwork_Superstr

Total cost of Labor Formwork Superstructure (shell) in 2017

dollar

295

Total_Labor_Formwork_Dome

Total cost of Labor Formwork Superstructure (dome) in 2017

dollar

296

Total_Labor_Formwork_Interior

Total cost of Labor Formwork Interior structure in 2017

dollar

297

Total_Labor_Maj_supp_embedments_Interior

Total cost of Labor Major Support Embedments Interior structure in 2017

dollar

298

Total_Labor_Reinforc_steel_Substr

Total cost of Labor Reinforc steel Substructure (base mat) in 2017

dollar

299

Total_Labor_Reinforc_steel_Superstr

Total cost of Labor Reinforc steel Superstructure (shell) in 2017

dollar

300

Total_Labor_Reinforc_steel_Dome

Total cost of Labor Reinforc steel Superstructure (dome) in 2017

dollar

301

Total_Labor_Reinforc_steel_Interior

Total cost of Labor Reinforc steel Interior structure in 2017

dollar

302

Total_Labor_Rubbing_surfaces_Superstr

Total cost of Labor Rubbing surfaces Superstructure (shell) in 2017

dollar

303

Total_Labor_Rubbing_surfaces_Dome

Total cost of Labor Rubbing surfaces Superstructure (dome) in 2017

dollar

304

Total_Labor_Rubbing_surfaces_Interior

Total cost of Labor Rubbing surfaces Interior structure in 2017

dollar

305

Total_Labor_Waterproofing_Substr

Total cost of Labor Waterproofing Substructure (base mat) in 2017

dollar

306

Total_Labor_Waterproofing_Superstr

Total cost of Labor Waterproofing Superstructure (shell) in 2017

dollar

307

Total_Labor_Waterproofing_Dome

Total cost of Labor Waterproofing Superstructure (dome) in 2017

dollar

308

Total_Labor_Welded_wire_fabric_Substr

Total cost of Labor Welded wire fabric Substructure (base mat) in 2017

dollar

309

Total_Labor_Lighting_Power

Total cost of Labor Lighting Power in 2017

dollar

310

Total_Labor_Plumb_drains

Total cost of Labor Plumb drains in 2017

dollar

311

Total_Labor_Special_HVAC

Total cost of Labor Special HVAC in 2017

dollar

312

Total_Labor_other

Total cost of Labor other in 2017

dollar

313

Total_Labor_Misc_steel_frames

Total cost of Labor miscellaneous steel frames in 2017

dollar

314

Total_Labor_React_cav_liner

Total cost of Labor Reactor cavity liner plate in 2017

dollar

315

Total_Labor_Struct_steel

Total cost of Labor Struct steel in 2017

dollar

316

Total_Labor_cont_liner

Total cost of Labor Containment liner in 2017

dollar

317

Total_Labor_fl_grate_handrail_stairs

Total cost of Labor Floor grating (galvanized), Handrail, Stair treads in 2017

dollar

318

Total_Labor_painting

Total cost of Labor painting in 2017

dollar

319

Total_Mat_Cadweld_Substr

Total cost of Material Cadweld Substructure (base mat) in 2017

dollar

320

Total_Mat_Cadweld_Superstr

Total cost of Material Cadweld Superstructure (shell) in 2017

dollar

321

Total_Mat_Cadweld_Dome

Total cost of Material Cadweld Superstructure (dome) in 2017

dollar

322

Total_Mat_Cadweld_Interior

Total cost of Material Cadweld Interior structure in 2017

dollar

323

Total_Mat_Concrete_Substr

Total cost of Material Concrete Substructure (base mat) in 2017

dollar

324

Total_Mat_Concrete_Superstr

Total cost of Material Concrete Superstructure (shell) in 2017

dollar

325

Total_Mat_Concrete_Dome

Total cost of Material Concrete Superstructure (dome) in 2017

dollar

326

Total_Mat_Concrete_Interior

Total cost of Material Concrete Interior structure in 2017

dollar

327

Total_Mat_Constr_joints_Substr

Total cost of Material Construction joints Substructure (base mat) in 2017

dollar

328

Total_Mat_Constr_joints_Superstr

Total cost of Material Construction joints Superstructure (shell) in 2017

dollar

329

Total_Mat_Constr_joints_Dome

Total cost of Material Construction joints Superstructure (dome) in 2017

dollar

330

Total_Mat_Constr_joints_Interior

Total cost of Material Construction joints Interior structure in 2017

dollar

331

Total_Mat_Embedded_steel_Substr

Total cost of Material Embedded steel Substructure (base mat) in 2017

dollar

332

Total_Mat_Embedded_steel_Superstr

Total cost of Material Embedded steel Superstructure (shell) in 2017

dollar

333

Total_Mat_Embedded_steel_Dome

Total cost of Material Embedded steel Superstructure (dome) in 2017

dollar

334

Total_Mat_Embedded_steel_Interior

Total cost of Material Embedded steel Interior structure in 2017

dollar

335

Total_Mat_Formwork_Substr

Total cost of Material Formwork Substructure (base mat) in 2017

dollar

336

Total_Mat_Formwork_Superstr

Total cost of Material Formwork Superstructure (shell) in 2017

dollar

337

Total_Mat_Formwork_Dome

Total cost of Material Formwork Superstructure (dome) in 2017

dollar

338

Total_Mat_Formwork_Interior

Total cost of Material Formwork Interior structure in 2017

dollar

339

Total_Mat_Maj_supp_embedments_Interior

Total cost of Material Major Support Embedments Interior structure in 2017

dollar

340

Total_Mat_Reinforc_steel_Substr

Total cost of Material Reinforc steel Substructure (base mat) in 2017

dollar

341

Total_Mat_Reinforc_steel_Superstr

Total cost of Material Reinforc steel Superstructure (shell) in 2017

dollar

342

Total_Mat_Reinforc_steel_Dome

Total cost of Material Reinforc steel Superstructure (dome) in 2017

dollar

343

Total_Mat_Reinforc_steel_Interior

Total cost of Material Reinforc steel Interior structure in 2017

dollar

344

Total_Mat_Rubbing_surfaces_Superstr

Total cost of Material Rubbing surfaces Superstructure (shell) in 2017

dollar

345

Total_Mat_Rubbing_surfaces_Dome

Total cost of Material Rubbing surfaces Superstructure (dome) in 2017

dollar

346

Total_Mat_Rubbing_surfaces_Interior

Total cost of Material Rubbing surfaces Interior structure in 2017

dollar

347

Total_Mat_Waterproofing_Substr

Total cost of Material Waterproofing Substructure (base mat) in 2017

dollar

348

Total_Mat_Waterproofing_Superstr

Total cost of Material Waterproofing Superstructure (shell) in 2017

dollar

349

Total_Mat_Waterproofing_Dome

Total cost of Material Waterproofing Superstructure (dome) in 2017

dollar

350

Total_Mat_Welded_wire_fabric_Substr

Total cost of Material Welded wire fabric Substructure (base mat) in 2017

dollar

351

Total_Mat_Lighting_Power

Total cost of Material Lighting Power in 2017

dollar

352

Total_Mat_Plumb_drains

Total cost of Material Plumb drains in 2017

dollar

353

Total_Mat_Special_HVAC

Total cost of Material Special HVAC in 2017

dollar

354

Total_Mat_other

Total cost of Material other in 2017

dollar

355

Total_Mat_Misc_steel_frames

Total cost of Material miscellaneous steel frames in 2017

dollar

356

Total_Mat_React_cav_liner

Total cost of Material Reactor cavity liner plate in 2017

dollar

357

Total_Mat_Struct_steel

Total cost of Material Struct steel in 2017

dollar

358

Total_Mat_cont_liner

Total cost of Material Containment liner in 2017

dollar

359

Total_Mat_fl_grate_handrail_stairs

Total cost of Material Floor grating (galvanized), Handrail, Stair treads in 2017

dollar

360

Total_Mat_painting

Total cost of Material painting in 2017

dollar

361

Sum_Labor_Cadweld

Total cost of Labor Cadweld

dollar

362

Sum_Labor_Concrete

Total cost of Labor Concrete

dollar

363

Sum_Labor_Constr_joints

Total cost of Labor Constr joints

dollar

364

Sum_Labor_Embedded_steel

Total cost of Labor Embedded steel

dollar

365

Sum_Labor_Formwork

Total cost of Labor Formwork

dollar

366

Sum_Labor_Maj_supp_embedments

Total cost of Labor Maj supp embedments

dollar

367

Sum_Labor_Reinforc_steel

Total cost of Labor Reinforc steel

dollar

368

Sum_Labor_Rubbing_surfaces

Total cost of Labor Rubbing surfaces

dollar

369

Sum_Labor_Waterproofing

Total cost of Labor Waterproofing

dollar

370

Sum_Labor_Welded_wire_fabric

Total cost of Labor Welded wire fabric

dollar

371

Sum_Mat_Cadweld

Total cost of Material Cadweld

dollar

372

Sum_Mat_Concrete

Total cost of Material Concrete

dollar

373

Sum_Mat_Constr_joints

Total cost of Material Constr joints

dollar

374

Sum_Mat_Embedded_steel

Total cost of Material Embedded steel

dollar

375

Sum_Mat_Formwork

Total cost of Material Formwork

dollar

376

Sum_Mat_Maj_supp_embedments

Total cost of Material Maj supp embedments

dollar

377

Sum_Mat_Reinforc_steel

Total cost of Material Reinforc steel

dollar

378

Sum_Mat_Rubbing_surfaces

Total cost of Material Rubbing surfaces

dollar

379

Sum_Mat_Waterproofing

Total cost of Material Waterproofing

dollar

380

Sum_Mat_Welded_wire_fabric

Total cost of Material Welded wire fabric

dollar

381

Tot_Labor_concr

Total cost of labor of containment construction

dollar

382

Tot_Labor_equipment

Total cost of labor of containment equipments

dollar

383

Tot_Labor_others

Total cost of labor of other non-concrete related items

dollar

384

Tot_Mat_concr

Total cost of material of containment construction

dollar

385

Tot_Mat_equipment

Total cost of material of containment equipments

dollar

386

Tot_Mat_others

Total cost of material of other non-concrete related items

dollar

387

Tot_Labor_containment

Total cost of labor of containment

dollar

388

Tot_Mat_containment

Total cost of material of containment

dollar